Custom R8M 2S CCM / Continuous Casting Plant with Ladle Turret
radius: R8M
Strand number : 2 strands
with ISO certification
advanced design
We can produce high quality continuous casting machines from 1 to 8 strands with the lowest equipment manufacturing cost.We can design, manufacture the up-to-date billet continuous casting machine in accordance with the user's steelmaking capacity, billet size, steel grades and the user's field conditions.
Description:
1. Basic standby technical parameters:
Steel billet casting machine radius  | 8m  | 
Strand quantity  | 2 strands  | 
Ladle support type  | Ladle turret or Ladle car  | 
Tundish carriage  | Semi-portal, cross sliding function  | 
Casting method  | Metering nozzle, open casting  | 
Secondary cooling  | Gas and water cooling , 2 adjusting circuit  | 
Withdrawal straightening machine  | Totally 5 roller, progressive straightening  | 
Roll table  | Chain group centralized drive  | 
Dummy bar  | Rigid, with self-adapting dummy bar head  | 
Billet cutting  | Hydraulic or flame cutting machine  | 
Billet conveying  | Group centralized live roller table  | 
Cooling bank type  | Simple cooling bed  | 
2. Technical process description and capacity of steel billet CCM
Induction furnace:
Nominal capacity  | 30T  | 
Tap-to-tap cycle  | 60min  | 
Furnace quantity  | 3sets  | 
Production capacity
Working days  | 330 days/year  | 
Average number of daily furnace  | 24/day  | 
Production capacity  | 300,000t/year  | 
3. Casting speed, productivity and strand quantity
R8m radius casting machine can cast steel groups of different specifications, the maximum casting speed is as follows:
Casting sectional area(mm)  | 180x180  | 200×200  | 220×220  | 
Casting speed(m/min)  | 1.6  | 1.8  | 2.0  | 
NO.  | Billet size  | Casting speed  | hourly output (tons)  | Daily output 20hour (tons)  | Annual output(300days) (tons)  | 
1  | 180×180  | 1.6m/min  | 21.98  | 439  | 131,700  | 
2  | 200×200  | 1.8m/min  | 27.13  | 543  | 162,900  | 
3  | 220×220  | 2.0m/min  | 36.47  | 729  | 218,700  | 
The calculation results is the ideal state of the production, please according to own actual situation of adjustment.
Steel grade  | Casting grade(m/min)  | Effective deformation rate(ε)  | Allowable deformation rate(εmax)  | 
Straight carbon steel  | 1.8~2.5  | Please refer to the computational table  | 0.25  | 
Low alloy steel  | 1.3~2.0  | Please refer to the computational table  | 0.15~0.2  | 
4. CCM equipment parts list
№  | Equipment name  | Weight  | Model and specification  | Unit  | |||
1  | Ladle turret  | 21T  | set  | 1  | |||
2  | Tundish arriage  | 12.5×2=25T  | set  | 2  | |||
3  | Tundish  | 6×2=12T  | set  | 2  | |||
4  | Slag Pot  | 2.5T  | set  | 1  | |||
5  | Long sleeve protection device  | 0.3T  | set  | 1  | |||
5  | Tundish baking  | 5.3×2=10.6T  | set  | 2  | |||
6  | Tundish nozzle  | set  | 2  | ||||
7  | Casting operation  | set  | 2  | ||||
8  | 150×150 Mould  | set  | 2  | ||||
9  | Mould cover  | set  | 2  | ||||
10  | Oscillator device  | set  | 2  | ||||
11  | Spray header  | set  | 2  | ||||
12  | Oriented segment  | set  | 2  | ||||
13  | Rigid dummy bar  | set  | 2  | ||||
14  | Dummy bar storage device  | set  | 2  | ||||
15  | Straightening and  | set  | 2  | ||||
16  | Straightening and  | set  | 1  | ||||
17  | Shears approach roller  | set  | 2  | ||||
18  | Billet clamping  | set  | 2  | ||||
19  | Torch cutting  | set  | 1  | ||||
20  | Collection cutting  | set  | 1  | ||||
21  | After cutting roller  | set  | 2  | ||||
22  | Transport rollerⅠ  | set  | 2  | ||||
23  | Transport rollerⅡ  | set  | 2  | ||||
24  | Knockout roller  | set  | 1  | ||||
25  | Fixed bezel  | set  | 1  | ||||
26  | Shifting steel  | 6m length  | set  | 1  | |||
27  | Collection cooling  | set  | 1  | ||||
28  | Caster body cooling  | include a backwash filter  | set  | 1  | |||
29  | Caster cover  | set  | 1  | ||||
30  | Automatic Length  | set  | 3  | ||||
31  | Gas source processor  | deal instrument gas  | set  | 1  | |||
32  | Steel platform  | 1  | |||||
Ⅱ  | Hydrauli,Lubrication,pneumatic system  | ||||||
1  | Host hydraulic station  | set  | 1  | ||||
2  | The billet hydraulic station  | set  | 1  | ||||
3  | Hydraulic lift tailgate  | set  | 2  | ||||
4  | Centralized grease lubrication station  | set  | 6  | ||||
5  | Hydraulic piping  | set  | 1  | ||||
6  | Lubrication piping  | set  | 1  | ||||
Ⅲ  | CCM 3-Electric  | ||||||
1  | Operating station  | ||||||
2  | Software Package  | ||||||
3  | PLC  | set  | 3  | ||||
4  | ET-200 PLC  | set  | |||||
                                 
                             |